Home > NPPs in Japan > Fukushima Daiichi-1

NPPs in Japan

Under decommissioning

Fukushima Daiichi-1

Closed Down: 2012-04-19
Age: 41
Reactor Type: BWR
Gross Output: 460MWe
Net Output: 439MWe
Owner: TEPCO
Operator: TEPCO
Date of order: 1966
Construction Start: 1967-04
Concrete placing: 1967-07-25
Initial Criticality: 1970-07-05
Grid connection: 1970-11-17
Commercial Operation: 1971-03-26
Main contractor: GE
Architect Engineer: EBASCO
Reactor System supplier: GE/GETSCO
Reactor Vessel supplier: GE/GETSCO/Toshiba/IHI
Incore Structure supplier: GE/GETSCO
Fuel supplier: GNF-J/NFI
Steam raising supplier: GE/GETSCO
Turbine generator supplier: GE/GETSCO
Civil works: various