Home > NPPs in Japan > Genkai-1

NPPs in Japan

Permanent shutdown

Genkai-1

Closed Down: 2015-04-27
Age: 39
Reactor Type: PWR
Gross Output: 559MWe
Net Output: 529MWe
Owner: Kyushu EPCO
Operator: Kyushu EPCO
Date of order: 1969
Construction Start: 1971-03
Concrete placing: 1971-09
Initial Criticality: 1975-01-28
Grid connection: 1975-02-14
Commercial Operation: 1975-10-15
Main contractor: MHI
Architect Engineer: MAPI
Reactor System supplier: MHI
Reactor Vessel supplier: MHI
Incore Structure supplier: MHI
Fuel supplier: MNF/NFI
Steam raising supplier: MHI
Turbine generator supplier: MHI
Civil works: various