Genkai-2

Closed Down: 2019-02-13
Age: 37
Reactor Type: PWR
Gross Output: 559MWe
Net Output: 529MWe
Owner: Kyushu EPCO
Operator: Kyushu EPCO
Date of order: 1976
Construction Start: 1976-06
Concrete placing: 1977-02
Initial Criticality: 1980-05-21
Grid connection: 1980-06-03
Commercial Operation: 1981-03-30
Main contractor: MHI
Architect Engineer: MAPI
Reactor System supplier: MHI
Reactor Vessel supplier: MHI
Incore Structure supplier: MHI
Fuel supplier: MNF/NFI
Steam raising supplier: MHI
Turbine generator supplier: MHI
Civil works: various