Home > NPPs in Japan > Hamaoka-4

NPPs in Japan

Outage since 2011-05-13

Hamaoka-4

Age: 31
Reactor Type: BWR
Gross Output: 1137MWe
Net Output: 1092MWe
Owner: Chubu EPCO
Operator: Chubu EPCO
Applications for Restart: 2014-02-14
Date of order: 1989
Construction Start: 1989-02
Concrete placing: 1989-10-13
Initial Criticality: 1992-12-02
Grid connection: 1993-01-27
Commercial Operation: 1993-09-03
Main contractor: Toshiba/Hitachi
Architect Engineer: Toshiba/Hitachi
Reactor System supplier: Toshiba
Reactor Vessel supplier: Toshiba/IHI
Incore Structure supplier: Toshiba
Fuel supplier: GNF-J/NFI
Steam raising supplier: Hitachi
Turbine generator supplier: Hitachi
Civil works: various