Home > NPPs in Japan > Hamaoka-5

NPPs in Japan

Outage since 2011-05-14

Hamaoka-5

Age: 19
Reactor Type: ABWR
Gross Output: 1380MWe
Net Output: 1325MWe
Owner: Chubu EPCO
Operator: Chubu EPCO
Date of order: 1999
Construction Start: 1999-03
Concrete placing: 2000-07-12
Initial Criticality: 2004-03-23
Grid connection: 2004-04-30
Commercial Operation: 2005-01-18
Main contractor: Toshiba/Hitachi
Architect Engineer: Toshiba
Reactor System supplier: Toshiba
Reactor Vessel supplier: Toshiba/IHI
Incore Structure supplier: Toshiba
Fuel supplier: GNF-J
Steam raising supplier: Hitachi
Turbine generator supplier: Hitachi
Civil works: various