NPPs in Japan
Outage since 2011-08-23
Kashiwazaki Kariwa-7
Age: |
27 |
Reactor Type: |
ABWR |
Gross Output: |
1356MWe |
Net Output: |
1315MWe |
Owner: |
TEPCO |
Operator: |
TEPCO |
Applications for Restart: |
2013-09-27 |
NRA's Approval for basic design: |
2017-12-27 |
Date of order: |
1991 |
Construction Start: |
1992-02 |
Concrete placing: |
1993-07-01 |
Initial Criticality: |
1996-11-01 |
Grid connection: |
1996-12-17 |
Commercial Operation: |
1997-07-02 |
Main contractor: |
Hitachi/GE/Toshiba |
Architect Engineer: |
Hitachi |
Reactor System supplier: |
Hitachi |
Reactor Vessel supplier: |
GE/Toshiba/Hitachi/BHK |
Incore Structure supplier: |
GE |
Fuel supplier: |
GNF-J/GNF-A |
Steam raising supplier: |
Toshiba |
Turbine generator supplier: |
GE |
Civil works: |
various |