Home > NPPs in Japan > Onagawa-3

NPPs in Japan

Outage since 2011-03-11

Onagawa-3

Age: 22
Reactor Type: BWR
Gross Output: 825MWe
Net Output: 796MWe
Owner: Tohoku EPCO
Operator: Tohoku EPCO
Date of order: 1997
Construction Start: 1996-09
Concrete placing: 1998-01
Initial Criticality: 2001-04-26
Grid connection: 2001-05-30
Commercial Operation: 2002-01-30
Main contractor: Toshiba/Hitachi
Architect Engineer: Toshiba
Reactor System supplier: Toshiba
Reactor Vessel supplier: Toshiba/IHI
Incore Structure supplier: Toshiba
Fuel supplier: Toshiba/GNF-J
Steam raising supplier: Hitachi
Turbine generator supplier: Hitachi
Civil works: various
JAIF TOP