Home > NPPs in Japan > Takahama-2
NPPs in Japan
Outage since 2011-11-25
Takahama-2
Age: |
49 |
Reactor Type: |
PWR |
Gross Output: |
826MWe |
Net Output: |
780MWe |
Owner: |
Kansai EPCO |
Operator: |
Kansai EPCO |
Applications for Restart: |
2015-03-17 |
NRA's Approval for basic design: |
2016-04-20 |
Date of order: |
1970 |
Construction Start: |
1971-02 |
Concrete placing: |
1971-03 |
Initial Criticality: |
1974-12-20 |
Grid connection: |
1975-01 |
Commercial Operation: |
1975-11-14 |
Main contractor: |
MSK |
Architect Engineer: |
Kansai EPCO/MAPI |
Reactor System supplier: |
MHI |
Reactor Vessel supplier: |
MHI |
Incore Structure supplier: |
MHI |
Fuel supplier: |
MNF |
Steam raising supplier: |
MHI |
Turbine generator supplier: |
MHI |
Civil works: |
various |