Home > NPPs in Japan > Tomari-3

NPPs in Japan

Outage since 2012-05-05

Tomari-3

Age: 15
Reactor Type: PWR
Gross Output: 912MWe
Net Output: 866MWe
Owner: Hokkaido EPCO
Operator: Hokkaido EPCO
Applications for Restart: 2013-07-08
Date of order: 2003
Construction Start: 2003-11
Concrete placing: 2004-07-24
Initial Criticality: 2009-03-03
Grid connection: 2009-03-20
Commercial Operation: 2009-12-22
Main contractor: MHI
Architect Engineer: MHI
Reactor System supplier: MHI
Reactor Vessel supplier: MHI
Incore Structure supplier: MHI
Fuel supplier: MNF
Steam raising supplier: MHI
Turbine generator supplier: MHI
Civil works: various
JAIF TOP